Ravenna Public Schools Bond Project
The bond
project for Ravenna Public Schools included additions and renovations
at three different locations. The project also
involved the construction of a new transportation and maintenance
facility adjacent to the high school.
Features
• Transportation facility and administrative
offices were raised to make room
for the expansion.
• New addition with 15 classrooms, a media center, multi-purpose
room, kitchen
and computer labs
• The Middle School campus site
layout was modified to facilitate traffic flow,
improve safety and ensure that the entire facility
is handicap accessible. • Three high school classroom wings were
remodeled.
• Renovation of gym, locker room facility, weight room, lobby and main entrance
Summary
Size:
Construction 74,700 sf
Renovation 38,000 sf
Cost:
$13.95 million
Schedule:
June 2000 – Aug. 2001
|