Ravenna Public Schools Bond Project

 

The bond project for Ravenna Public Schools included additions and renovations at three different locations. The project also involved the construction of a new transportation and maintenance facility adjacent to the high school.

 

Features

• Transportation facility and administrative offices were raised to make room

for the expansion.

• New addition with 15 classrooms, a media center, multi-purpose room, kitchen

and computer labs

• The Middle School campus site layout was modified to facilitate traffic flow,

improve safety and ensure that the entire facility is handicap accessible.

• Three high school classroom wings were remodeled.
• Renovation of gym, locker room facility, weight room, lobby and main entrance

 

Summary

Size:

Construction 74,700 sf

Renovation 38,000 sf

Cost:

$13.95 million

Schedule:

June 2000 – Aug. 2001