Mercy General Hospital Special Delivery Center

 

A Team 200, design/build approach helped to further compress an already aggressive construction schedule. Working with Tower-Pinkster-Titus Associates, Muskegon Construction Company completed design and construction in only 13 months. Despite a number of owner-initiated changes during construction, the project was completed seven weeks ahead of the original schedule.

 

Features

• Six labor/delivery/recovery/post-partum (LDRP) rooms
• Six post-partum patient rooms
• Matching nursery, triage testing room, a surgical suite, locker rooms and offices
• Electrical and mechanical systems are housed in the 4,000-square-foot basement level.

 

Summary

Size: 16,700 sf

Cost: $3,500,000

Schedule: