Mercy General Hospital Special Delivery Center
A Team
200, design/build approach helped to further compress an already
aggressive construction schedule. Working with Tower-Pinkster-Titus
Associates, Muskegon Construction Company completed design and
construction in only 13 months. Despite a number of owner-initiated
changes during construction, the project was completed seven
weeks ahead of the original schedule.
Features
• Six labor/delivery/recovery/post-partum (LDRP) rooms
• Six post-partum patient rooms
• Matching nursery, triage testing room, a surgical suite, locker
rooms and offices
• Electrical and mechanical systems are housed in the 4,000-square-foot
basement level.
Summary
Size: 16,700 sf
Cost: $3,500,000
Schedule:
|
|