The first phase of summer work has been completed
for Fruitport Community Schools. On September 15, 2003 the voters
in the Fruitport
School District approved an $8.4 million millage request for
improvements to all the buildings in the district. This is the
second project Muskegon Construction Company has done for the
valued client having previously done their 1997 bond project.
Approximately $5.5 million of the money raised will go into construction
and the remainder into technology up-grades, buses and other
equipment. Approximately $2.6 million worth of work was completed
in the summer 2004 including mechanical up-grades, new boilers,
improved lighting, new flooring and entrances at several district
schools. It also included lighting at the soccer field and improved
lighting of the football stadium, as well as a concession building
and press box at the baseball diamond. The remainder of the work
is scheduled for completion next summer.
|
|